Add an EVM to the system
The Custody Infrastructure system allows adding EVM coins to Impenetrable Vault, in both Cold-driven and MPC-driven modes. In Cold-Driven mode the coin is added directly to the Impenetrable Vault.
However, in MPC-Driven mode the coin must first be added to the MPC and then imported to the Impenetrable Vault. For information see, Importing an EVM, ERc-20 or TRC-20 in MPC-Driven modeImporting an EVM, ERc-20 or TRC-20 in MPC-Driven mode
The Impenetrable Vault includes a list of preset EVM coins that can be loaded automatically into the system. If a coin is not included in this list, you can add a new coin manually.
Both scenarios are described below.
Only admin users can activate EVM coins.
Version 17 now supports up to 999 EVMs, ERC-20s and TRC-20s coins on the system, effectively removing the limitations present in previous versions.
To add a new EVM to the system:
- Log into the cold vault as an admin.
- Click Create EVM on the Coin Management panel. The Add EVM Coin dialog opens.

From here, predefined EVMs can be loaded onto the system and new EVMs can be defined.
Confirming the New EVM
After being properly configured, the new EVM will appear in the desktop and mobile app, both on the dashboard and in the Coin Managment areas.